When an application and drawings/plans are received by Omega Rail Management, they are reviewed for accuracy. After they are approved by this office, the documents are forwarded to the appropriate railroad departments for further review. Several railroad departments will perform the review during the process to determine whether the application can be approved. The review and subsequent permitting process generally takes three to six weeks. If the application is approved, the applicant will receive an agreement via U.S. Mail or, in some cases, by email which will be in Adobe Acrobat format (PDF). The agreement will outline all of the conditions and terms required by the railroad along with the insurance requirements. The agreements have previously been reviewed by railroad counsel and as such, cannot be changed without an additional review by the railroads counsel. Should a review become necessary, additional fees will apply.
|